The National Energy Regulator of South Africa (NERSA) announced last week that it is in the process of developing the regulatory framework on small-scale renewable embedded generation as well as the guidelines on the electricity reseller tariffs.
 
Any tariff approved by NERSA for the small-scale renewable embedded generation and electricity resellers will be an interim tariff as the structure, level and the rates will change after the process has been finalised.
 
The timeline for the process to be followed is illustrated below:

Regulatory Framework on Small-Scale Renewable Embedded Generation Milestones

Anticipated Date

Discussion document sent to stakeholders for comments

12 December 2014

Date comments to be received from stakeholders

7 January 2015

Consultation Paper issued for comments

16 January 2015

Comments received from stakeholders

16 February 2015

Conduct public hearings

April 2015

Approval of regulatory framework by the Energy Regulator

May 2015

Guidelines on the Electricity Reseller Tariff Milestones

Anticipated Date

Consultation paper issued for comments

16 January 2015

Comments received from stakeholders

16 February 2015

Conduct public hearings

April 2015

Approval of regulatory framework by the Energy Regulator