
Trump Administration Executive Order (EO) Tracker
On July 27, 2023, U.S. electricity regulators issued a Final Rule to streamline and speed up the connection of new power projects to the electric grid – implementing reforms that could ease the growing backlog of proposed projects from transmission providers and interconnection customers. At the end 2022, more than 2,000 GW of generation and storage projects were waiting in interconnection queues throughout the country. The Federal Energy Regulatory Commission (“FERC”) finalized the long-awaited Final Rule, Order 2023, intended to reform how and when power generation projects get connected to the electric grid. This is the first major change to FERC’s interconnection requirements in two decades.
New power projects – namely new wind, solar and battery storage plants – have faced an average wait of up to five years to connect to the grid. FERC’s Order 2023 is aimed at increasing queue efficiency and alleviating the current five-year average wait time for projects to connect to the grid. Those projects have been stuck in massive backlogs while grid managers conduct interconnection studies needed to gauge how bringing them online would affect the broader system and determine whether any upgrades are needed. According to FERC Chairman Willie Phillips, “[t]his new rule will enable America’s vast power generation resources to connect to the grid in a reliable, efficient, transparent and timely manner, and in doing so, help provide more reliable, resilient and affordable electricity for all consumers.” He referred to the Final Rule as “a watershed moment for our nation’s transmission grid.”
In underscoring the need for these reforms, Chairman Phillips noted that the GWs of generation and storage that were waiting in interconnection queues is as much electricity generation capacity as all the power plants now operating around the country.
The Final Rule – at almost 1,500 pages – requires all public utilities to adopt revised pro forma generator interconnection procedures and agreements to ensure that interconnection customers can connect to the transmission system in a reliable, efficient, transparent, and timely manner, and to prevent undue discrimination. Specifically, it contains several key areas of reforms, including, among other changes, shifting from a "first come, first served" to a "first ready" approach – meaning projects that are prepared with land rights and permits would move ahead of those that are not. The Final Rule will also impose financial and other conditions to secure a place in the interconnect queue and establish penalties per day for grid operators if they fail to complete interconnection studies on time. FERC will also allow projects to be studied in clusters instead of one-by-one in hopes of speeding up the process.
We summarize some of the key takeaways from the Final Rule in more detail below:
The final rule builds on FERC’s Notice of Proposed Rulemaking (“NOPR”) issued in 2022. Notably, in the Final Rule, FERC declined to adopt the NOPR proposals pertaining to informational interconnection studies, shared network upgrades, the optional resource solicitation study, and the alternative transmission technologies annual report. The Final Rule also does not adopt the proposed non-financial commercial readiness criteria from the NOPR, instead requiring only financial demonstrations of commercial readiness.
The Final Rule will take effect 60 days after its publication in the Federal Register, and compliance filings from transmission providers to implement the new requirements will be due 90 days after publication. We will be monitoring for any additional updates as the final rule is set to be published in the coming days.
For more information on the new interconnection rule, contact Neil Chatterjee, or Stephanie Fishman, Associate.